Software Used on this Project
Project Overview
Australia’s Queensland State Government established a design brief and an extremely challenging “not to be exceeded” budget for a new bridge in the state capital, Brisbane, to “provide a link from the Queensland Gallery of Modern Art (GoMA) in the South Bank Precinct to Tank Street in the Central Business District”. The objective was to deliver a landmark pedestrian and cycle bridge – “architecturally striking”, and sympathetic and complementary to its prominent location.
The creative partnership of contractor Baulderstone, engineer Arup, and architect Cox Rayner produced the scheme for the 430m long tensegrity Kurilpa Bridge (Aboriginal for “place for water rats”), a bold fusion of art and science featuring a striking array of masts, cables, and flying steel spars, winning the design competition. The factors that influenced the judging panel’s decision included the sculptural quality and aesthetic “fit” with the GoMA, the visual lightness, the structural efficiency, and the innovative originality of the design.
The use of “tensegrity” (the term was coined by Buckminster Fuller) in a major structure has been something of a holy grail to architects and engineers around the world for decades, and the successful completion of the Kurilpa Bridge represents a genuine world first.
Key statistics
- Bridge deck 430m long x 6.5m clear width between handrails
- 500m3 of concrete and 500 tonnes of steel
- Nearly 7km of high strength steel cables
Overview of the Project
Concept Design
The team considered a wide range of possible forms and materials that might comply with the tight geometric restrictions of the site, clearance, and disabled access. The resulting maximum deck level and minimum underside effectively limited the structural depth to less than 1m.
The potential solutions identified were cable-stayed, arch, suspension, tube, and tensegrity mast-and-cable. The large masts required for the cable-stayed were too visually dominant given the proximity to the GoMA though and the ground conditions too poor for arch and suspension options. The tube option was promising as it avoided these problems and could integrate the continuous awning requirements, but was potentially difficult to construct over the deep and fast-flowing river.
Inspired by Buckminster Fuller and the work of sculptor Kenneth Snelson, the Arup conceived tensegrity solution satisfied the need for visually light, shallow, and buildable form that would sit comfortably beside the GoMA while being innovative, whimsical, apparently random, and radically different from the norm.
Superstructure form and details
Overall the Kurilpa Bridge has three main sections: the 120m Kurilpa Point approach, the tensegrity bridge itself (three spans of 58m, 128m, and 45m), and the 82m Tank Street approach. The approaches are separated from the central tensegrity bridge by expansion joints and bearings, allowing the three main sections to expand and contract separately.
The tensegrity bridge comprises of composite steel and concrete deck structure, the series of steel masts and cables, and the integrated array of steel ties, flying struts (spars) and steel-framed tensegrity canopy.
The overall structure is approximately balanced, eliminating the need for massive abutments and allowing construction by the balanced cantilever method. This allowed for unconventionally subtle tie-down points at the outer ends to counterweight the large central span as well as compact and slender supports.
The precast deck panels are joined by in situ concrete stitches that are supported by and work compositely with rolled steel I-sections. The edge beams, which are separated from the deck, are fabricated steel box sections. These include a curved steel plate fairing on the outer face to ensure aerodynamic stability under all service and ultimate design wind speeds.
Pairs of major raking tubular steel masts spring from the main support piers on either side of the main span, setting the locations of an approximately coplanar array of minor secondary masts. The major and minor masts are offset from the perpendicular both longitudinally and transversely, thus both preventing cable/mast or cable/cable clashes and providing the signature “randomness” without significantly reducing structural efficiency. Secondary cables connected to flying struts, themselves pure tensegrity elements (supported only by cables), provide lateral restraint to the masts.
The tensegrity array of flying struts and cables that hovers above and beside the deck fulfils three critical functions:
- It suspends the canopy, allowing it to float above the deck with no apparent means of support.
- It laterally restrains the tops of all the masts, preventing them from buckling sideways under the loads arising from the suspension of the deck plus lateral and seismic forces.
- It works in unison with all the masts and cables to resist twisting and lateral forces arising from patch loads on the deck (i.e. crowds), wind and earthquakes
The various tensegrity bridge elements are as follows:
- Masts: fabricated tubular steel sections up to 30m long with section sizes 610-905mm diameter
- Major mast cables: high-strength spiral wound galvanised wire ropes 30-80mm diameter
- Spars: circular hollow sections up to 23m long with section sizes 457-508mm diameter
- Spar cables: high-strength stainless steel spiral wound cables 19-32mm diameter
How Oasys proved invaluable
A key aspect of bridges that span over major river and road corridors is the need for the structure to support itself at all stages of the erection without temporary falsework. Working closely with the contractor the Arup team designed the bridge to be cantilevered out from each of the two major river piers, effectively using the permanent structure to construct itself.
The superstructure erection had to be planned with the utmost precision to ensure that the bridge would assume its theoretically correct geometry when the thousands of prefabricated pieces were bolted together. The deflections of cables are notoriously difficult to predict accurately, particularly initially when the cable tensions are small – the effective extensions of a cable with low tension are large, whereas in a highly stressed cable they are small. The non-linear axial stiffness can be visualised by thinking about how it is easy to move the end of a sagging rope by pulling, whereas pulling a taut rope produces little movement.
When erecting large complex structures. Two basic approaches can be taken to ensure that the completed project has the correct geometry. The first is to constantly monitor the position of the structure during construction, making adjustments along the way. The second is to accurately prefabricate all the components, and then by scenario planning and sophisticated analysis that connecting the together without adjustment will result in an acceptable final geometry. For the Kurilpa Bridge the complexity of the structure and the time constraints necessitated the second option, with the contractors forced to rely on the accuracy of the designers’ predictions. Arup achieved this using purpose-written software that linked into GSA via the COM interface, allowing thousands of construction stage analyses to be run and checked.
The accuracy of the modelling was demonstrated when the two bridge halves met precisely at mid-span as predicted by the GSA analysis.
Additional information
Initial analyses of the construction sequencing for Kurilpa Bridge were completed using the staging module in GSA. This allowed the design team to easily modify and adjust the model parameters for the final structure, without manually updating the construction models. The module allowed the team to superimpose results from successive stages providing a good indication of stress development and deflection in the structure.
Towards the later stages of the project, when more accurate analysis was required and the final structure was finalised, Arup moved to using separate GSA analysis models for each construction stage. The analysis models were de-constructed from the final model and non-linear analysis run using GSA’s dynamic relaxation solver. This allowed for extensive lack of fit analyses to be undertaken using the construction length tolerances for bridge elements and determine the envelope of bridge position during construction. This facilitated the real time monitoring of construction progress and identification of potential issues before unacceptable stresses were built into the indeterminate structure.
The lack-of-fit analyses were generated using the GSA COM interface, which allows the modification of the GSA model through a Microsoft excel interface. Dead load analysis identified critical compression and tension elements, which allowed us to create positive and negative lack-of-fit load cases in the construction analysis model. Influence of lack-of-fit analysis on member load distribution in construction was checked using load combinations, subtracting the ideal structure results from lack-of-fit results. Arup assessed changes in stress distribution and determined a reasonable envelope for bridge position during construction.
Member checking for construction phase were driven by a Microsoft Excel spreadsheet which using a macro directly output member force and moment results from each GSA model. These allowed automatic calculation of element utilisations and identification of critical stages during construction.
The lack-of-fit study for the full completed structure was completed using the GSA Com interface driven from an excel sheet.
Structural Dynamics
The bridge is relatively light, but has a comparatively long main span and a complex array of masts and cables. All this plus its unique design meant that it could be subject to unusual dynamic or aerodynamic effects with no precedents or “rules-of-thumb” upon which to draw. As a result, extensive wind tunnel, dynamic and fatigue analyses were required to comprehensively investigate and resolve all potential dynamic phenomena.
Dynamic Properties
A linear modal analysis was carried out, and the finite element model included detailed modelling of the concrete deck, piers and abutments, and small amplitude displacement foundation stiffnesses. Due to the geometry, several cables in the support structure are fairly low stressed and careful consideration was given to the effective cable stiffnesses to account for cable sag.
The dynamic behaviour was found to be complex due to the proportion of structure self-weight above the deck (masts, cables, spars and canopy). This led to many lateral torsional modes and significant coupling between mast and deck motions.
The lateral modes were found to be sensitive to the lateral stiffness of the piers supporting the major masts, so a sensitivity study was carried out to bound the lateral stiffness, including consideration of variation in soil stiffness and the potential for future scour around the foundations. Following the completion of the bridge structure, modal identification tests using ambient vibrations were carried out to identify the frequencies of key modes and found to have good correlation with the GSA analysis.
Aeroelastic stability of deck
Aeroelasticity covers a range of effects in bluff body aerodynamics whereby structural motion interacts with the fluid flow causing the motion. Classical flutter, galloping, and vortex shedding, for example, need to be considered in designing long-span bridge decks. Kurilpa Bridge has a very shallow deck and closely spaced, low-frequency vertical and torsional modes. This led to concerns that the deck could become unstable aerodynamically at wind speeds lower than the ultimate design wind speed, so this aspect of the design was investigated. While normal for major long-span road bridges, this is not commonly required for shorter-span bridges.
Wind tunnel studies were commissioned specifically to look at the aeroelastic stability of the proposed cross-section, while sectional wind tunnel tests were carried out using a spring-supported model of the bridge with mass and stiffness adjusted to represent the critical modes of vibration derived from the GSA analysis. These tests lead to the adoption of bull-nose fairings, which gave both an acceptable aerodynamic performance and improved aesthetics.
Vortex shedding excitation of masts and spars
As vortices are shed from alternate sides of bluff bodies in fluid flow, an oscillating force is induced. If the natural frequency of the structure is close to the frequency of this force, resonance may occur and, if unchecked, vortex shedding can lead to noticeable responses and/or fatigue problems. Excitation may occur on different elements at different times depending on the local wind speeds, natural frequencies and element diameters.
Assessment of susceptibility
The Kurilpa Bridge masts were assessed for aeroelastic stability under vortex shedding. The masts are partially fixed at their bases and the connections have geometries that are potentially sensitive to fatigue damage.
The Vickery-Basu method, as incorporated in several codes and standards (most clearly in the new Eurocode 1), was used for assessing vortex shedding response. It compares a predicted “negative aerodynamic damping” with the inherent structural damping of the structure; when the latter exceeds the former, the member is considered stable. Since the masts are mostly welded (and the bolted joints are under compression), the inherent damping will be low and may start to approach levels of material damping of perhaps only 0.10-0.15% of critical.
The vortex shedding susceptibility calculations carried out were based on structural damping of 0.24% critical (as specified in Eurocode 1) in addition to any positive aerodynamic damping arising from movements of the rest of the structure, but included a safety factor of two against instability to account for the possibility of lower damping levels.
The modal properties were taken from the bridge GSA model, and 250 structural modes were considered – taking in all that were potentially at risk from vortex shedding excitation. The major masts were found to be stable, but the minor masts potentially unstable.
Design solution
Measures were taken to reduce the risk of excessive vortex shedding response and potential structural damage of the minor masts. Helical strakes, adding additional mass to the masts, or adding damping, were all considered as ways to control vortex shedding response. Additional damping was the preferred solution as it had the least impact on the aesthetics and proposed structure.
Hanging chain dampers were not possible due to the inclination of the masts, so external ring impact dampers were used. TMDs were considered, but the difficulty of tuning to each mast frequency made them impractical. The ring dampers were designed in close consultation with the architect for minimal impact on aesthetics and lighting, and ability to be maintained or replaced at a future date. Each has a steel annulus weighing between 100kg and 250kg (depending upon mast size and frequency), supported by three steel cables just over half-way up the mast, and able to move relative to it. Impacts between the mast and the ring dissipate the energy that any vortex shedding excitation puts into the masts, and are softened by visco-elastic pads that absorb energy and reduce sound.
Pedestrian-induced vibration
The vertical and lateral response of the bridge under dynamic pedestrian loads was checked in GSA in accordance with current international best practice in addition to meeting the requirements of AS5100.2 2004. The following design scenarios were considered to ensure the bridge’s serviceability for normal use:
- single pedestrian walking at footfall rates of 1.0-2.6Hz
- continuous pedestrian streams and dense walking crowds up to 1.7 people/m2
- a small jogging group of up to 10 people.
The responses of the bridge were predicted to be acceptable with the exception of potential synchronous lateral excitation (SLE) due to crowd loading.
Background to synchronous lateral excitation
Synchronous lateral excitation is the phenomenon whereby pedestrians may “lock in” to the lateral sway of bridge decks, causing significant lateral motions. SLE will tend to happen on bridges with low frequency lateral modes that directly coincide with the frequency of lateral forces due to walking.
Pedestrian lateral force input has been measured experimentally and found to increase linearly with deck velocity, effectively introducing a negative damping term to the equation of motion. The bridge thus becomes laterally unstable if the energy input by the crowd during each vibration cycle exceeds the energy that may be dissipated through damping in the structure. This occurs when the crowd walking across reaches a critical number.
There is ongoing research into the exact mechanism of “lock-in” and lateral pedestrian load modelling, but the design methodology proposed following the remedial works on the London Millennium Bridge has proved robust in assessing the susceptibility of bridges to SLE and designing mitigation solutions.
Assessment of susceptibility
As Kurilpa Bridge is a major urban footbridge that may experience dense crowds during a public event, a design crowd density of 1.7 people/m2 (5000+ pedestrians) was chosen (above this, walking becomes difficult).
All lateral modes with frequencies below 1.5Hz predicted for Kurilpa Bridge were checked for susceptibility to SLE, and the critical crowd density that would cause the bridge to become laterally unstable was calculated in each case. If the density predicted was >1.7 people/m2, SLE would not occur, but if the density was above 1.7 people/m2, SLE was considered possible.
Remedial measures were then investigated that would either stiffen the mode out of the range of concern or increase the critical crowd density to >1.7 people/m2. The calculations assumed a structural damping level of 0.7% critical. This is higher than the typical 0.5% critical damping assumed for steel-framed bridges due to the nature of the supporting structure, but was confirmed following measurements on the completed structure.
Design solution
To reduce susceptibility to SLE, ways to increase the lateral stiffness of the river piers and the structural damping of the lateral modes were considered. Lateral tuned mass dampers (TMDs) were selected as the most economical and least visually intrusive solution. Three 3.2 tonne lateral TMDs under the bridge deck at the centre of the main span were designed to provide sufficient additional damping for all modes in the full range of pier lateral stiffnesses predicted during design when tuned with respect to the measured frequencies of the lateral modes. The design takes account of the fact that TMDs add less damping to modes with higher modal masses, but less damping is required in these modes as more people are required to cause instability.
Conclusion
Kurilpa Bridge is a landmark project that is architecturally striking yet sympathetic to its prominent location. Not only has the bridge achieved the client’s requirement that it not detract from the GoMA, but it is acclaimed as a fine piece of civic sculpture in its own right.
Opened on time and on budget, it breaks new ground through the incorporation of tensegrity structure for the first time in a major bridge. Importantly, the design does not obscure the view of the river but enhances its beauty and accessibility, and its connections. Pedestrians and cyclists enjoy a dynamic experience, with the projecting decks affording spectacular views and creating intriguing urban spaces.
In January 2011, southern and central Queensland suffered from disastrous flooding, including a major flood in Brisbane. An extraordinary combination of torrential rain over the river catchment and high tides resulted in the Brisbane River reaching levels approximately 1m above the 100-year flood level. The floods caused an unprecedented amount of damage to buildings and infrastructure, and tragically resulted in a number of deaths. Kurilpa Bridge, however, was not damaged by the flood, and reopened to the public as soon as water levels receded.
2011 World Architecture Fesitval - Best Transport Project Royal Australian Institute of Architects Queensland Chapter, Karl Langer Award for Urban Design Australia Steel Institute, Queensland 2010 Steel Awards: Winner, Structural Engineering Steel Building Award Australia Steel Institute, Queensland 2010 Steel Awards: High Commendation Infrastructure Projects Structural Engineering Steel Design Award Engineers Australia Queensland 2010: Engineering Excellence Award for Project Infrastructure over $20M Engineers Australia Queensland 2010: Engineering Excellence Award for Innovation Engineers Australia Queensland 2010: Australian Engineering Excellence Award 2010 Consultant Australia Awards for Excellence – “Project of the Year” and Gold Awards (Transport and Civil)